May 1, 2026
- Linder Road will be closed November 18th through mid-May 2026.
- Linder Rd - Excavation ongoing. Lights bases set. Preparing for sidewalk. Sidewalk being placed. Curb & Gutter ongoing. Finishing up Irrigation ditches. Signals removed. Block wall started April 20th.
- Foothills Bridge - Rail remaining.
- Dry Creek Bridge - Complete. Backfill ongoing. Shoe fly removed.
- Floating Feather and Linder Roundabout - Veolia working on the new water line.