May 13, 2026

Linder Rd

  • Sidewalk being placed.
  • Curb & gutter ongoing.
  • Block wall started April 20th.
  • Paving anticipated the week of May 11th.
  • Paving on the 16th in middle section at SH-44 for 2nd phase signal configuration.
  • Traffic signal switch 17th.

Foothills Bridge

  • Rail remaining.

Dry Creek Bridge

  • Complete.

Floating Feather and Linder Roundabout

  • Veolia working on new water line.
  • Closure starting May 18th.
  • Milling Road starting the week of the 18th.