May 13, 2026
Linder Rd
- Sidewalk being placed.
- Curb & gutter ongoing.
- Block wall started April 20th.
- Paving anticipated the week of May 11th.
- Paving on the 16th in middle section at SH-44 for 2nd phase signal configuration.
- Traffic signal switch 17th.
Foothills Bridge
- Rail remaining.
Dry Creek Bridge
- Complete.
Floating Feather and Linder Roundabout
- Veolia working on new water line.
- Closure starting May 18th.
- Milling Road starting the week of the 18th.