May 29, 2026
East side of Linder Rd - Sidewalk remaining. Block wall installation ongoing.
West side of Linder Rd - Excavation and concrete removal. Storm drain ongoing.
Foothills Bridge - Rail remaining.
Dry Creek Bridge - Complete.
Floating Feather and Linder Roundabout - Veolia is working on the new water line. The intersection closure started May 18th. Utilities are relocating facilities.