November 13, 2026

East side of Linder Rd to Saguaro

  • Sidewalk installation remaining.

West side of Linder Rd to Saguaro

  • Curb complete from State Street to Saguaro Dr.
  • Sidewalk installation ongoing.
  • Paving is ongoing.

Saguaro Dr to Floating Feather

  • Road base installation is ongoing.
  • Curb is being placed.
  • Wall is being installed.
  • Sidewalk being placed after wall installation is complete.

Floating Feather and Linder Roundabout

  • Underground power installation is complete.
  • Finishing the installation of the subgrade.
  • Curb is being placed on the roundabout.
  • Concrete paving is complete.

Linder Road anticipated being open to Beacon Light by December 4th, weather dependent.