October 16, 2026
East side of Linder Rd to Saguaro
- Sidewalk remaining
West side of Linder Rd to Saguaro
- Curb complete from State Street to Saguaro Dr.
- Sidewalk installation ongoing.
- Bottom lift of paving complete.
- Block wall being reset.
Saguaro Dr to Floating Feather
- Road base ongoing.
- Curb being placed.
- Wall being installed.
Floating Feather and Linder Roundabout
- Underground power complete.
- Finishing subgrade.
- Curb being placed on roundabout.
- Concrete intersection anticipated to start October 15th.