October 16, 2026

East side of Linder Rd to Saguaro

  • Sidewalk remaining

West side of Linder Rd to Saguaro

  • Curb complete from State Street to Saguaro Dr.
  • Sidewalk installation ongoing.
  • Bottom lift of paving complete.
  • Block wall being reset.

Saguaro Dr to Floating Feather

  • Road base ongoing.
  • Curb being placed.
  • Wall being installed.

Floating Feather and Linder Roundabout

  • Underground power complete.
  • Finishing subgrade.
  • Curb being placed on roundabout.
  • Concrete intersection anticipated to start October 15th.