October 2, 2026

East side of Linder Rd to Saguaro

  • Sidewalk still remaining.

West side of Linder Rd to Saguaro

  • Curb complete from State Street to Saguaro Dr.
  • Sidewalk installation ongoing.
  • Bottom lift of paving complete.
  • Block wall being reset.

Saguaro Dr to Floating Feather

  • Pole bases placed and school flashers installed.
  • Road base installation ongoing.
  • Curb being placed.

Dry Creek Bridge - Complete. Rail installation ongoing.

Floating Feather and Linder Roundabout

  • Underground power conduit installation ongoing.
  • Finishing the subgrade.
  • Curb being placed on roundabout.
  • Concrete intersection installation anticipated starting Oct 15th.