East side of Linder Rd to Saguaro - Sidewalk remaining.
West side of Linder Rd to Saguaro - Curb complete from State Street to Saguaro Dr. Sidewalk ongoing. Bottom lift of paving complete. Block wall being reset.
Saguaro Dr to Floating Feather - Road base ongoing. Curb being placed. Wall being installed. Sidewalk being placed after wall complete.
Floating Feather and Linder Roundabout - Underground power complete. Finishing subgrade. Curb being placed on roundabout. Concrete Paving - 1st placement scheduled for October 21st. Work is weather-dependent. 2nd placement anticipated for October 23rd.