October 30, 2026
East side of Linder Rd to Saguaro
- Sidewalk installation remaining.
West side of Linder Rd to Saguaro
- Curb is complete from State Street to Saguaro Dr.
- Sidewalk installation is ongoing.
- Bottom lift of paving is complete.
Saguaro Dr to Floating Feather
- Road base installation is ongoing.
- Curb is being placed.
- Wall is being installed.
- Sidewalk is being placed after wall is complete.
Floating Feather and Linder Roundabout
- Underground power is complete.
- Finishing subgrade.
- Curb is being placed on the roundabout.
- Concrete paving is ongoing.
Linder Road anticipated being open to Beacon Light by December 5th.