September 11, 2026
East side of Linder Rd
- Sidewalk remaining.
- Block wall installation ongoing.
- SH-44 block wall ongoing.
West side of Linder Rd
- Curb being placed from State Street to Saguaro Dr. - complete.
- Sidewalk installation ongoing.
- Bottom lift complete.
Saquaro Dr to Floating Feather
- Pole bases placed.
- Road base ongoing.
- School flashers installed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain installed.
- Underground power conduit installation ongoing.
- Development will install Sewer line starting August 7th - Ongoing.
- Forming and placing sidewalk once sewer is complete.
Share September 11, 2026 on Facebook
Share September 11, 2026 on X (formerly Twitter)
Share September 11, 2026 on Linkedin
Email September 11, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends