East side of Linder Rd

  • Sidewalk remaining.
  • Block wall installation ongoing.
  • SH-44 block wall ongoing.

West side of Linder Rd

  • Curb being placed from State Street to Saguaro Dr. - complete.
  • Sidewalk installation ongoing.
  • Bottom lift complete.

Saquaro Dr to Floating Feather

  • Pole bases placed.
  • Road base ongoing.
  • School flashers installed.

Dry Creek Bridge - Complete. Rail installation ongoing.

Floating Feather and Linder Roundabout

  • Utilities relocating facilities.
  • Road sub-graded.
  • Storm drain installed.
  • Underground power conduit installation ongoing.
  • Development will install Sewer line starting August 7th - Ongoing.
  • Forming and placing sidewalk once sewer is complete.