September 17, 2026

East side of Linder Rd to Saguaro

  • Sidewalk installation remaining.
  • Block wall installation ongoing.

West side of Linder Rd to Saguaro

  • Curb complete from State Street to Saguaro Dr.
  • Sidewalk installation is ongoing.
  • Bottom lift of paving is complete.
  • Block wall is being reset.

Saguaro Dr to Floating Feather

  • Pole bases placed and school flashers are installed.
  • Road base installation ongoing.

Dry Creek Bridge - Complete. Rail installation ongoing.

Floating Feather and Linder Roundabout

  • Storm drain is installed.
  • Underground power conduit installation ongoing.
  • Sewer line installation for the adjacent development is complete.
  • Finishing subgrade.
  • Forming and placing sidewalk.