September 24, 2026

East side of Linder Rd to Saguaro

  • Sidewalk installation remaining.

West side of Linder Rd to Saguaro

  • Curb installation complete from State Street to Saguaro Dr.
  • Sidewalk installation ongoing.
  • Bottom lift of paving complete.
  • Block wall being reset.

Saguaro Dr to Floating Feather

  • Pole bases are placed and school flashers are installed.
  • Road base installation ongoing.
  • Curb being placed.

Dry Creek Bridge - Complete. Rail installation ongoing.

Floating Feather and Linder Roundabout

  • Storm drain has been installed.
  • Underground power conduit installation is ongoing.
  • Finishing subgrade.
  • Curb being placed at the roundabout.