September 24, 2026
East side of Linder Rd to Saguaro
- Sidewalk installation remaining.
West side of Linder Rd to Saguaro
- Curb installation complete from State Street to Saguaro Dr.
- Sidewalk installation ongoing.
- Bottom lift of paving complete.
- Block wall being reset.
Saguaro Dr to Floating Feather
- Pole bases are placed and school flashers are installed.
- Road base installation ongoing.
- Curb being placed.
Dry Creek Bridge - Complete. Rail installation ongoing.
Floating Feather and Linder Roundabout
- Storm drain has been installed.
- Underground power conduit installation is ongoing.
- Finishing subgrade.
- Curb being placed at the roundabout.
Share September 24, 2026 on Facebook
Share September 24, 2026 on X (formerly Twitter)
Share September 24, 2026 on Linkedin
Email September 24, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends