September 3, 2026

East side of Linder Rd

  • Sidewalk remaining.
  • Block wall ongoing.
  • SH-44 block wall ongoing.

West side of Linder Rd

  • Curb being placed from State Street to Saguaro Dr. - complete.
  • Sidewalk ongoing.
  • Bottom lift complete.

Saquaro Dr to Floating Feather

  • Pole bases being placed.
  • Road base ongoing.
  • School Flashers installed.

Foothills Bridge - Rail installed.

Dry Creek Bridge - Complete. Rail ongoing.

Floating Feather and Linder Roundabout

  • Utilities relocating facilities.
  • Road sub-graded.
  • Storm drain installed.
  • Underground power conduit ongoing.
  • Development will install sewer line starting August 7th - Ongoing.
  • Forming and placing sidewalk once sewer is complete.