September 3, 2026
East side of Linder Rd
- Sidewalk remaining.
- Block wall ongoing.
- SH-44 block wall ongoing.
West side of Linder Rd
- Curb being placed from State Street to Saguaro Dr. - complete.
- Sidewalk ongoing.
- Bottom lift complete.
Saquaro Dr to Floating Feather
- Pole bases being placed.
- Road base ongoing.
- School Flashers installed.
Foothills Bridge - Rail installed.
Dry Creek Bridge - Complete. Rail ongoing.
Floating Feather and Linder Roundabout
- Utilities relocating facilities.
- Road sub-graded.
- Storm drain installed.
- Underground power conduit ongoing.
- Development will install sewer line starting August 7th - Ongoing.
- Forming and placing sidewalk once sewer is complete.