May 5, 2023

  • Locust Grove and Victory Intersection - Water line ongoing. Placing subgrade down Victory.
  • Locust Grove - Nine Mile Creek - Complete. Installing waterline on Coastline, will work North. Subgrading and placing base behind water installation.
Share May 5, 2023 on Facebook Share May 5, 2023 on Twitter Share May 5, 2023 on Linkedin Email May 5, 2023 link

Project is substantially complete