April 7, 2023

  • Locust Grove and Victory intersection - concrete footings placed March 8th. Water line work - ongoing. Idaho Power relocating lines - anticipated complete by April 1st. Box culvert placed March 16th - Wingwalls placed. Backfilling culvert. Placing of the subgrade on the 27th.
  • Locust Grove - Nine Mile Creek - complete.
  • Excavating heading north from Doberman - ongoing. Placing base west side of road.
  • Excavating west side of Locust Grove between Mastiff and Overland - ongoing. Installing waterline on Coastline.
Share April 7, 2023 on Facebook Share April 7, 2023 on Twitter Share April 7, 2023 on Linkedin Email April 7, 2023 link

Project is substantially complete