  • Locust Grove and Victory intersection - East, West, and South lanes open.
  • Placing pedestrian rail at roundabout.
  • Locust Grove - Paving complete between Charolais and Victory. Excavating East side of Peacock and Charolais Dr. Placing curb and sidewalk. Installation of school flashing beacon ongoing.
Share August 11, 2023 on Facebook Share August 11, 2023 on Twitter Share August 11, 2023 on Linkedin Email August 11, 2023 link

Project is substantially complete