February 10, 2023
- Locust Grove intersection - Excavating for structure at Ten Mile Creek.
- Water line ongoing.
- Intermountain Gas ongoing. Idaho Power relocating lines.
- Locust Grove - Closed from Charolais to Victory started January 16th.
- Nine Mile Creek headwalls excavated.
- Form footings for headwalls.
- Footing placed February 7th.
- Excavation heading north from Doberman ongoing.