February 17, 2023
- Locust Grove and Victory Intersection - Excavating for structure at Ten Mile Creek.
- Water line ongoing.
- Intermountain gas ongoing.
- Idaho Power relocating lines.
- Locust Grove - Bridge out at Charlaois starting February 16-18.
- Local traffic only on Locust Grove.
- Nine Mile Creek headwalls excavated.
- Installing Nine Mile culvert during closure.
- Excavation heading north from Doberman ongoing.