February 17, 2023
- Locust Grove and Victory Intersection - Excavating for structure at Ten Mile Creek.
- Water line ongoing.
- Intermountain gas ongoing.
- Idaho Power relocating lines.
- Locust Grove - Bridge out at Charlaois starting February 16-18.
- Local traffic only on Locust Grove.
- Nine Mile Creek headwalls excavated.
- Installing Nine Mile culvert during closure.
- Excavation heading north from Doberman ongoing.
Share February 17, 2023 on Facebook
Share February 17, 2023 on Twitter
Share February 17, 2023 on Linkedin
Email February 17, 2023 link
Project is substantially complete