February 3, 2023
- Locust Grove and Victory - utility companies relocating their lines.
- Culvert on Victory removed.
- Water line ongoing.
- Intermountain gas relocating their facilities.
- Locust Grove to Charolais closed.
- Local traffic only through to Locust Grove.
- Nine Mile Creek headwalls excavated.
- Forming footings for headwalls.
- Excavation heading north from Lake Creek.
Interested in reviewing the latest aerial footage of the project? Click here.
Share February 3, 2023 on Facebook
Share February 3, 2023 on Twitter
Share February 3, 2023 on Linkedin
Email February 3, 2023 link
Project is substantially complete