February 3, 2023
- Locust Grove and Victory - utility companies relocating their lines.
- Culvert on Victory removed.
- Water line ongoing.
- Intermountain gas relocating their facilities.
- Locust Grove to Charolais closed.
- Local traffic only through to Locust Grove.
- Nine Mile Creek headwalls excavated.
- Forming footings for headwalls.
- Excavation heading north from Lake Creek.