January 13, 2023
- Locust Grove and Victory intersection - utility companies relocating their lines.
- Culvert on Victory being removed.
- Water installation ongoing.
- Locust Grove - Closure from Charloais Drive to Victory starting January 16th.
- Asphalt removal starting on the 18th.
- Culvert replacement starting the 26th.