June 2, 2023
- Locust Grove and Victory intersection - placing sidewalk, curb and gutter - 3/4 base.
- Paving anticipated the week of the 26th.
- Island curb after paving.
- Locust Grove - underground facilities complete. Establishing subgrade and placing base gravel.