June 2, 2023

  • Locust Grove and Victory intersection - placing sidewalk, curb and gutter - 3/4 base.
  • Paving anticipated the week of the 26th.
  • Island curb after paving.
  • Locust Grove - underground facilities complete. Establishing subgrade and placing base gravel.
Share June 2, 2023 on Facebook Share June 2, 2023 on X (formerly Twitter) Share June 2, 2023 on Linkedin Email June 2, 2023 link

Project is substantially complete