June 23, 2023
- Locust Grove and Victory intersection - curb, gutter complete. Roundabout concrete ongoing. Paving anticipated the week of June 26th. Island curb will be installed after paving. Round about curb being placed.
- Locust Grove - Gravel being placed. Sidewalk will be placed starting June 26th. Curb placement will begin after sidewalk.
Share June 23, 2023 on Facebook
Share June 23, 2023 on X (formerly Twitter)
Share June 23, 2023 on Linkedin
Email June 23, 2023 link
Project is substantially complete