June 23, 2023

  • Locust Grove and Victory intersection - curb, gutter complete. Roundabout concrete ongoing. Paving anticipated the week of June 26th. Island curb will be installed after paving. Round about curb being placed.
  • Locust Grove - Gravel being placed. Sidewalk will be placed starting June 26th. Curb placement will begin after sidewalk.
Share June 23, 2023 on Facebook Share June 23, 2023 on Twitter Share June 23, 2023 on Linkedin Email June 23, 2023 link

Project is substantially complete