June 9, 2023
- Locust Grove and Victory Intersection - Placing sidewalk, curb and gutter and 3/4 base. Paving anticipated the week of June 26th. Island curb after paving.
- Locust Grove - Underground facilities complete. Establishing subgrade. Placing base gravel.
Interested in reviewing the progress of the project? Review the latest drone footage.
Share June 9, 2023 on Facebook
Share June 9, 2023 on Twitter
Share June 9, 2023 on Linkedin
Email June 9, 2023 link
Project is substantially complete