March 10, 2023

  • Locust Grove and Victory Intersection - concrete footage placed on March 8th.
  • Water line ongoing.
  • Intermountain Gas ongoing.
  • Idaho Power relocating lines - anticipated complete by April 1st.
  • Placing culvert starting March 16th.
  • Locust Grove - 9 Mile Creek - Placing rebar for headwalls. Concrete planned for March 9th.
  • Excavation heading north on Doberman - ongoing.
  • Placing base on west side of road.
  • Excavating west side of Locust Grove between Mastiff and Overland.