March 10, 2023

  • Locust Grove and Victory Intersection - concrete footage placed on March 8th.
  • Water line ongoing.
  • Intermountain Gas ongoing.
  • Idaho Power relocating lines - anticipated complete by April 1st.
  • Placing culvert starting March 16th.
  • Locust Grove - 9 Mile Creek - Placing rebar for headwalls. Concrete planned for March 9th.
  • Excavation heading north on Doberman - ongoing.
  • Placing base on west side of road.
  • Excavating west side of Locust Grove between Mastiff and Overland.
Share March 10, 2023 on Facebook Share March 10, 2023 on Twitter Share March 10, 2023 on Linkedin Email March 10, 2023 link

Project is substantially complete

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>