  • Locust Grove and Victory Intersection - Concrete footings placed March 8th.
  • Water line - ongoing.
  • Intermountain Gas - ongoing.
  • Idaho power relocating lines - anticipated completion by April 1st.
  • Box culvert placed March 16th.
  • Locust Grove and Nine Mile Creek - Backfill ongoing.
  • Excavation heading north from Doberman - ongoing.
  • Placing base on west side of road.
  • Excavating west side of Locust Grove between Mastiff and Overland - ongoing.

Interested in viewing the project from above? Click here to view the drone footage of the project.

Share March 24, 2023 on Facebook Share March 24, 2023 on X (formerly Twitter) Share March 24, 2023 on Linkedin Email March 24, 2023 link

Project is substantially complete