March 3, 2023

  • Excavating for structure at Ten Mile Creek.
  • Setting forms for footing.
  • Water line ongoing.
  • Intermountain gas ongoing.
  • Idaho Power relocating lines.
  • Locust Grove - Nine Mile Creek - Placing rebar for headwalls.
  • Excavation heading north from Doberman - ongoing.
  • Placing base on west side of the road.
  • Excavating west side of Locust Grove between Mastiff and Overland.

Interested in reviewing the progress of the project? Review the latest drone footage.

Share March 3, 2023 on Facebook Share March 3, 2023 on Twitter Share March 3, 2023 on Linkedin Email March 3, 2023 link

Project is substantially complete