May 12, 2023

  • Locust Grove and Victory intersection - Water line ongoing. Placing subgrade down Victory. Sidewalk being placed.
  • Locust Grove - Nine Mile Creek - complete. Installing waterline on Coastline working north. Sub grading and placing base behind water installation.
Share May 12, 2023 on Facebook Share May 12, 2023 on X (formerly Twitter) Share May 12, 2023 on Linkedin Email May 12, 2023 link

Project is substantially complete