- Locust Grove and Victory Intersection - water line ongoing. Placing subgrade down Victory. Sidewalk being placed.
- Locust Grove - Nine Mile Creek - Complete.
- Installing water line on Coastline, working north.
- Sub-grading and placing base behind water installation.
Interested in reviewing the progress of the project? Review the latest drone footage.
Share May 19, 2023 on Facebook
Share May 19, 2023 on Twitter
Share May 19, 2023 on Linkedin
Email May 19, 2023 link
Project is substantially complete