August 18, 2023
- Road closure started August 2nd.
- Contractor removed bridge.
- Dewatering anticipated to start August 14th.
- Utility companies relocating lines.
Share August 18, 2023 on Facebook
Share August 18, 2023 on Twitter
Share August 18, 2023 on Linkedin
Email August 18, 2023 link
This project is substantially complete.