October 12, 2023
- Footings placed
- Dewatering ongoing
- Precast boxes set
- Closure pour anticipated on October 13th
- Backfill after closure pour is cleared
Share October 12, 2023 on Facebook
Share October 12, 2023 on Twitter
Share October 12, 2023 on Linkedin
Email October 12, 2023 link
This project is substantially complete.