October 12, 2023

  • Footings placed
  • Dewatering ongoing
  • Precast boxes set
  • Closure pour anticipated on October 13th
  • Backfill after closure pour is cleared
Share October 12, 2023 on Facebook Share October 12, 2023 on Twitter Share October 12, 2023 on Linkedin Email October 12, 2023 link

This project is substantially complete. 