This project is substantially complete. 

The Ada County Highway District (ACHD) will start construction on Mallard Drive, north of Park Center Boulevard, as early as mid-June or as late as August 2023. Construction is anticipated to be completed in December 2023.*

Project Description

  • As part of the Bridge Maintenance Program, ACHD will remove and replace the existing Mallard Drive culvert over Loggers Creek
  • Reconstruct the adjacent pedestrian ramps to meet modern standards
  • Install pedestrian railings over the Mallard Drive culvert to increase safety

Construction Impacts

  • Temporary road closes
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with the homeowners to minimize construction impacts

*Construction schedules may change due to the high demand for contractors, labor, and supplies.

The Ada County Highway District (ACHD) will start construction on Mallard Drive, north of Park Center Boulevard, as early as mid-June or as late as August 2023. Construction is anticipated to be completed in December 2023.*

Project Description

  • As part of the Bridge Maintenance Program, ACHD will remove and replace the existing Mallard Drive culvert over Loggers Creek
  • Reconstruct the adjacent pedestrian ramps to meet modern standards
  • Install pedestrian railings over the Mallard Drive culvert to increase safety

Construction Impacts

  • Temporary road closes
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with the homeowners to minimize construction impacts

*Construction schedules may change due to the high demand for contractors, labor, and supplies.

This project is substantially complete. 

  • December 1, 2023

    Share December 1, 2023 on Facebook Share December 1, 2023 on Twitter Share December 1, 2023 on Linkedin Email December 1, 2023 link
    • Mallard was paved on November 21st.
    • Rail has been installed.
    • Minor work remains, including landscaping and pavement markings.
  • November 22, 2023

    Share November 22, 2023 on Facebook Share November 22, 2023 on Twitter Share November 22, 2023 on Linkedin Email November 22, 2023 link

    Mallard is closed for the duration of the project.

    • Mallard paved November 21st.
    • Landscaping and rail remaining.
  • November 17, 2023

    Share November 17, 2023 on Facebook Share November 17, 2023 on Twitter Share November 17, 2023 on Linkedin Email November 17, 2023 link

    ► Mallard is closed for the duration of the project.

    ► Topping slab placed

    ► Sidewalk curb being placed

    ► Asphalt paving anticipated Nov 20th

  • November 9, 2023

    Share November 9, 2023 on Facebook Share November 9, 2023 on Twitter Share November 9, 2023 on Linkedin Email November 9, 2023 link
    • Sidewalk and asphalt being removed and replaced.
    • Prepping deck for topping slab.
    • Rip rap placed, out of the creek.
  • November 3, 2023

    Share November 3, 2023 on Facebook Share November 3, 2023 on Twitter Share November 3, 2023 on Linkedin Email November 3, 2023 link
    • Dewatering ongoing.
    • Backfilling ongoing.
    • Rip rap placement after backfill.
    • Sidewalk and asphalt being removed.
  • October 27, 2023

    Share October 27, 2023 on Facebook Share October 27, 2023 on Twitter Share October 27, 2023 on Linkedin Email October 27, 2023 link
    • Dewatering ongoing
    • Backfilling ongoing
    • Rip rap placement after backfill
  • October 20, 2023

    Share October 20, 2023 on Facebook Share October 20, 2023 on Twitter Share October 20, 2023 on Linkedin Email October 20, 2023 link
    • Footings placed.
    • Dewatering ongoing.
    • Precast boxes set.
    • Closure pour anticipated October 17th.
    • Backfill after closure pour is cured.
  • October 12, 2023

    Share October 12, 2023 on Facebook Share October 12, 2023 on Twitter Share October 12, 2023 on Linkedin Email October 12, 2023 link
    • Footings placed
    • Dewatering ongoing
    • Precast boxes set
    • Closure pour anticipated on October 13th
    • Backfill after closure pour is cleared
  • October 6, 2023

    Share October 6, 2023 on Facebook Share October 6, 2023 on Twitter Share October 6, 2023 on Linkedin Email October 6, 2023 link
    • Footings placed.
    • Dewatering ongoing.
    • Placing Rip Rap.
    • Anticipated box placement week of October 9th.
  • September 29, 2023

    Share September 29, 2023 on Facebook Share September 29, 2023 on Twitter Share September 29, 2023 on Linkedin Email September 29, 2023 link
    • Footings placed.
    • Dewatering ongoing.