Mallard Drive Bridge

Share Mallard Drive Bridge on Facebook Share Mallard Drive Bridge on Twitter Share Mallard Drive Bridge on Linkedin Email Mallard Drive Bridge link

This project is substantially complete. 

The Ada County Highway District (ACHD) will start construction on Mallard Drive, north of Park Center Boulevard, as early as mid-June or as late as August 2023. Construction is anticipated to be completed in December 2023.*

Project Description

  • As part of the Bridge Maintenance Program, ACHD will remove and replace the existing Mallard Drive culvert over Loggers Creek
  • Reconstruct the adjacent pedestrian ramps to meet modern standards
  • Install pedestrian railings over the Mallard Drive culvert to increase safety

Construction Impacts

  • Temporary road closes
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with the homeowners to minimize construction impacts

*Construction schedules may change due to the high demand for contractors, labor, and supplies.

The Ada County Highway District (ACHD) will start construction on Mallard Drive, north of Park Center Boulevard, as early as mid-June or as late as August 2023. Construction is anticipated to be completed in December 2023.*

Project Description

  • As part of the Bridge Maintenance Program, ACHD will remove and replace the existing Mallard Drive culvert over Loggers Creek
  • Reconstruct the adjacent pedestrian ramps to meet modern standards
  • Install pedestrian railings over the Mallard Drive culvert to increase safety

Construction Impacts

  • Temporary road closes
  • Lane restrictions with flaggers
  • Pedestrian detours and sidewalk closures
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with the homeowners to minimize construction impacts

*Construction schedules may change due to the high demand for contractors, labor, and supplies.

This project is substantially complete. 

  • September 22, 2023

    Share September 22, 2023 on Facebook Share September 22, 2023 on Twitter Share September 22, 2023 on Linkedin Email September 22, 2023 link
    • Contractor has removed bridge
    • Footings being prepped for concrete
    • Dewatering ongoing
  • September 8, 2023

    Share September 8, 2023 on Facebook Share September 8, 2023 on Twitter Share September 8, 2023 on Linkedin Email September 8, 2023 link
    • Road closure started Aug 2nd
    • Contractor removed bridge
    • Dewatering ongoing
    • Veolia water line relocation ongoing
  • August 31, 2023

    Share August 31, 2023 on Facebook Share August 31, 2023 on Twitter Share August 31, 2023 on Linkedin Email August 31, 2023 link
    • Road closure started August 2nd
    • Contractor removed bridge
    • Dewatering ongoing
    • Veolia anticipated water line relocating August 28th
  • August 25, 2023

    Share August 25, 2023 on Facebook Share August 25, 2023 on Twitter Share August 25, 2023 on Linkedin Email August 25, 2023 link
    • Road closure started August 2nd.
    • Contractor removed bridge.
    • Dewatering ongoing.
    • Veolia anticipated water line relocation August 28th.
  • August 18, 2023

    Share August 18, 2023 on Facebook Share August 18, 2023 on Twitter Share August 18, 2023 on Linkedin Email August 18, 2023 link
    • Road closure started August 2nd.
    • Contractor removed bridge.
    • Dewatering anticipated to start August 14th.
    • Utility companies relocating lines.
  • August 11, 2023

    Share August 11, 2023 on Facebook Share August 11, 2023 on Twitter Share August 11, 2023 on Linkedin Email August 11, 2023 link
    • Contractor removed bridge.
    • Dewatering anticipated starting August 14th.
    • Utility companies relocating lines.
  • August 4, 2023

    Share August 4, 2023 on Facebook Share August 4, 2023 on Twitter Share August 4, 2023 on Linkedin Email August 4, 2023 link
    • Road closure started August 2nd.
    • Contractor clearing and grubbing.
    • Dewatering anticipated starting August 8th.
  • July 28, 2023

    Share July 28, 2023 on Facebook Share July 28, 2023 on Twitter Share July 28, 2023 on Linkedin Email July 28, 2023 link
    • Utility work has been started in advance of the project.
    • Construction work is expected to begin early August.
    • Detour map below