April 2, 2026

  • Munger Road closed during bridge replacement.
  • Speed bumps have been installed in the adjacent neighborhoods.
  • Speed trailer added.
  • Munger Road - Excavating for road base.
  • South Bridge - precast placed. Backfilled.
  • Installing Bridge #2001 - Backfilling. Removing dewatering set up. Replacing irrigation pipe.
Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link

This project is substantially complete