Munger Road Bridges

Share Munger Road Bridges on Facebook Share Munger Road Bridges on Twitter Share Munger Road Bridges on Linkedin Email Munger Road Bridges link

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culverts on Munger Road, south of New Hope Road, starting the beginning of January.* Construction is expected to be complete in summer 2026.

Project Highlights

  • Removing and replacing the existing bridges on Munger Road
  • Reconstructing the roadway
  • Filling in the sidewalk gap on the east side of Munger Road, between W. Shortcreek Street and N. Catamaran Way, including new curb, gutter, and pedestrian ramps
  • Improving stormwater facilities to enhance drainage

Construction Impacts

  • Munger Road will be closed during construction
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culverts on Munger Road, south of New Hope Road, starting the beginning of January.* Construction is expected to be complete in summer 2026.

Project Highlights

  • Removing and replacing the existing bridges on Munger Road
  • Reconstructing the roadway
  • Filling in the sidewalk gap on the east side of Munger Road, between W. Shortcreek Street and N. Catamaran Way, including new curb, gutter, and pedestrian ramps
  • Improving stormwater facilities to enhance drainage

Construction Impacts

  • Munger Road will be closed during construction
  • Pedestrian detours and sidewalk closures
  • Lane restrictions with flaggers
  • Neighborhood traffic calming will be in place to discourage cut-through traffic on residential streets
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • April 2, 2026

    Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Munger Road - Excavating for road base.
    • South Bridge - precast placed. Backfilled.
    • Installing Bridge #2001 - Backfilling. Removing dewatering set up. Replacing irrigation pipe.
  • March 26, 2026

    Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 link
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • Munger Road - Excavating for road base.
    • South Bridge precast placed. Backfilled.
    • Installing Bridge #2001 - Backfilling. Removing dewatering set up.
  • March 19, 2026

    Share March 19, 2026 on Facebook Share March 19, 2026 on Twitter Share March 19, 2026 on Linkedin Email March 19, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • South Bridge precast placed.
    • Backfilling and placing riprap.
    • Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
  • March 13, 2026

    Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • South Bridge precast placed. Backfilling and placing riprap.
    • Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
  • March 6, 2026

    Share March 6, 2026 on Facebook Share March 6, 2026 on Twitter Share March 6, 2026 on Linkedin Email March 6, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • South Bridge precast placed.
    • Forming and placing aprons.
    • Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.
  • February 27, 2026

    Share February 27, 2026 on Facebook Share February 27, 2026 on Twitter Share February 27, 2026 on Linkedin Email February 27, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • South bridge removed.
    • South Bridge precast placed.
    • Forming footings and wingwalls.
    • Installing Bridge #2001 - Excavated. Placing precast week of the February 23rd.
  • February 19, 2026

    Share February 19, 2026 on Facebook Share February 19, 2026 on Twitter Share February 19, 2026 on Linkedin Email February 19, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • South bridge removed.
    • South Bridge precast placed. Forming footings and wingwalls.
    • Installing Bridge #2001. Excavated. Placing precast week of the February 23rd.
  • February 12, 2026

    Share February 12, 2026 on Facebook Share February 12, 2026 on Twitter Share February 12, 2026 on Linkedin Email February 12, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • South bridge removed.
    • Preparing for bridge placement.
    • Installing Bridge #2001 mid February.
  • February 5, 2026

    Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Speed trailer added.
    • Dewatering measures installed.
    • South bridge removed.
    • Preparing for bridge placement.
    • Installing Bridge #2001 mid February.
    • Sewer work started February 2nd.
  • January 30, 2026

    Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 link
    • Munger Road closed during bridge replacement.
    • Speed bumps have been installed in the adjacent neighborhoods.
    • Dewatering measures installed.
    • South bridge removed.
    • Prepping for bridge placement.
    • Installing Bridge #2001 mid February.
    • Starting sewer work February 2nd.
Page last updated: 02 Apr 2026, 01:14 PM