This project is substantially complete
-
Share May 21, 2026 on Facebook
Share May 21, 2026 on X (formerly Twitter)
Share May 21, 2026 on Linkedin
Email May 21, 2026 link
Munger Road
- Paved.
- Signs and Stripes remaining.
- Landscaping ongoing.
Munger Road
- Paved.
- Signs and Stripes remaining.
- Landscaping ongoing.
This project is substantially complete
-
Share May 13, 2026 on Facebook
Share May 13, 2026 on X (formerly Twitter)
Share May 13, 2026 on Linkedin
Email May 13, 2026 link
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Paved. Signs and Stripes remaining. Landscaping ongoing.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Paved. Signs and Stripes remaining. Landscaping ongoing.
This project is substantially complete
-
Share May 8, 2026 on Facebook
Share May 8, 2026 on X (formerly Twitter)
Share May 8, 2026 on Linkedin
Email May 8, 2026 link
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
This project is substantially complete
-
Share May 1, 2026 on Facebook
Share May 1, 2026 on X (formerly Twitter)
Share May 1, 2026 on Linkedin
Email May 1, 2026 link
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Sidewalk and curb being placed. Asphalt paving is scheduled for May 11th.
- South Bridge #1005 complete.
- Bridge #2001 complete.
This project is substantially complete
-
Share April 24, 2026 on Facebook
Share April 24, 2026 on X (formerly Twitter)
Share April 24, 2026 on Linkedin
Email April 24, 2026 link
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
This project is substantially complete
-
Share April 16, 2026 on Facebook
Share April 16, 2026 on X (formerly Twitter)
Share April 16, 2026 on Linkedin
Email April 16, 2026 link
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Munger Road - Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 complete.
- Bridge #2001 complete.
This project is substantially complete
-
Share April 10, 2026 on Facebook
Share April 10, 2026 on X (formerly Twitter)
Share April 10, 2026 on Linkedin
Email April 10, 2026 link
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 - complete.
- Bridge #2001 - complete.
- Munger Road closed during the project.
- Speed bumps and speed trailer have been installed in the adjacent neighborhoods.
- Base placed. Prepping for curb & sidewalk.
- South Bridge #1005 - complete.
- Bridge #2001 - complete.
This project is substantially complete
-
Share April 2, 2026 on Facebook
Share April 2, 2026 on X (formerly Twitter)
Share April 2, 2026 on Linkedin
Email April 2, 2026 link
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Munger Road - Excavating for road base.
- South Bridge - precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up. Replacing irrigation pipe.
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Munger Road - Excavating for road base.
- South Bridge - precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up. Replacing irrigation pipe.
This project is substantially complete
-
Share March 26, 2026 on Facebook
Share March 26, 2026 on X (formerly Twitter)
Share March 26, 2026 on Linkedin
Email March 26, 2026 link
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- Munger Road - Excavating for road base.
- South Bridge precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- Munger Road - Excavating for road base.
- South Bridge precast placed. Backfilled.
- Installing Bridge #2001 - Backfilling. Removing dewatering set up.
This project is substantially complete