February 19, 2026
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Speed trailer added.
- Dewatering measures installed.
- South bridge removed.
- South Bridge precast placed. Forming footings and wingwalls.
- Installing Bridge #2001. Excavated. Placing precast week of the February 23rd.
Share February 19, 2026 on Facebook
Share February 19, 2026 on X (formerly Twitter)
Share February 19, 2026 on Linkedin
Email February 19, 2026 link
This project is substantially complete