January 30, 2026
- Munger Road closed during bridge replacement.
- Speed bumps have been installed in the adjacent neighborhoods.
- Dewatering measures installed.
- South bridge removed.
- Prepping for bridge placement.
- Installing Bridge #2001 mid February.
- Starting sewer work February 2nd.