March 26, 2026

  • Speed bumps have been installed in the adjacent neighborhoods.
  • Speed trailer added.
  • Dewatering measures installed.
  • Munger Road - Excavating for road base.
  • South Bridge precast placed. Backfilled.
  • Installing Bridge #2001 - Backfilling. Removing dewatering set up.