March 6, 2026

  • Munger Road closed during bridge replacement.
  • Speed bumps have been installed in the adjacent neighborhoods.
  • Speed trailer added.
  • Dewatering measures installed.
  • South Bridge precast placed.
  • Forming and placing aprons.
  • Installing Bridge #2001. Excavated. Precast installed. Grouting and forming for closure pour.