This project is substantially complete.
-
Share October 4, 2024 on Facebook
Share October 4, 2024 on X (formerly Twitter)
Share October 4, 2024 on Linkedin
Email October 4, 2024 link
- Last Ped ramp being placed October 2nd.
- Pavement markings October 3rd.
- Anticipated completion October 4th.
- Last Ped ramp being placed October 2nd.
- Pavement markings October 3rd.
- Anticipated completion October 4th.
This project is substantially complete.
-
Share September 26, 2024 on Facebook
Share September 26, 2024 on X (formerly Twitter)
Share September 26, 2024 on Linkedin
Email September 26, 2024 link
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Standing poles ongoing.
- Ped ramp replacement ongoing.
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Standing poles ongoing.
- Ped ramp replacement ongoing.
This project is substantially complete.
-
Share September 20, 2024 on Facebook
Share September 20, 2024 on X (formerly Twitter)
Share September 20, 2024 on Linkedin
Email September 20, 2024 link
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Standing poles ongoing.
- Ped ramp replacement ongoing.
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Standing poles ongoing.
- Ped ramp replacement ongoing.
This project is substantially complete.
-
Share September 13, 2024 on Facebook
Share September 13, 2024 on X (formerly Twitter)
Share September 13, 2024 on Linkedin
Email September 13, 2024 link
- Curb being placed - Pole bases placed.
- Working on cabinet on southwest corner.
- Standing poles September 12th.
- Ped ramp replacement ongoing.
- Curb being placed - Pole bases placed.
- Working on cabinet on southwest corner.
- Standing poles September 12th.
- Ped ramp replacement ongoing.
This project is substantially complete.
-
Share September 6, 2024 on Facebook
Share September 6, 2024 on X (formerly Twitter)
Share September 6, 2024 on Linkedin
Email September 6, 2024 link
- Curb being placed - Pole bases placed.
- Working on cabinet on southwest corner.
- Ped ramp replacement ongoing.
- Curb being placed - Pole bases placed.
- Working on cabinet on southwest corner.
- Ped ramp replacement ongoing.
This project is substantially complete.
-
Share August 30, 2024 on Facebook
Share August 30, 2024 on X (formerly Twitter)
Share August 30, 2024 on Linkedin
Email August 30, 2024 link
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Ped ramp replacement ongoing.
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Ped ramp replacement ongoing.
This project is substantially complete.
-
Share August 23, 2024 on Facebook
Share August 23, 2024 on X (formerly Twitter)
Share August 23, 2024 on Linkedin
Email August 23, 2024 link
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Ped ramp replacement ongoing.
- Curb being placed.
- Pole bases placed.
- Working on cabinet on southwest corner.
- Ped ramp replacement ongoing.
This project is substantially complete.
-
Share August 15, 2024 on Facebook
Share August 15, 2024 on X (formerly Twitter)
Share August 15, 2024 on Linkedin
Email August 15, 2024 link
- Curb being placed.
- Pole bases placed.
- Working on Cabinet on southwest corner.
- Southwest pedestrian ramp anticipated being placed August 21st.
- Curb being placed.
- Pole bases placed.
- Working on Cabinet on southwest corner.
- Southwest pedestrian ramp anticipated being placed August 21st.
This project is substantially complete.
-
Share August 9, 2024 on Facebook
Share August 9, 2024 on X (formerly Twitter)
Share August 9, 2024 on Linkedin
Email August 9, 2024 link
- Boring complete.
- Contractor working on signal poles on northeast and southeast corners.
- Veolia removed fire hydrant on southeast corner.
- Poles bases placed on east side.
- Pole bases being prepped on west side.
- Boring complete.
- Contractor working on signal poles on northeast and southeast corners.
- Veolia removed fire hydrant on southeast corner.
- Poles bases placed on east side.
- Pole bases being prepped on west side.
This project is substantially complete.
-
Share August 2, 2024 on Facebook
Share August 2, 2024 on X (formerly Twitter)
Share August 2, 2024 on Linkedin
Email August 2, 2024 link
- Boring complete.
- Contractor working on signal poles on northeast and southeast corners.
- Veolia removed fire hydrant on southeast corner.
- Poles bases placed on east side.
- Pole bases being prepped on west side.
- Boring complete.
- Contractor working on signal poles on northeast and southeast corners.
- Veolia removed fire hydrant on southeast corner.
- Poles bases placed on east side.
- Pole bases being prepped on west side.
This project is substantially complete.