August 9, 2024
- Boring complete.
- Contractor working on signal poles on northeast and southeast corners.
- Veolia removed fire hydrant on southeast corner.
- Poles bases placed on east side.
- Pole bases being prepped on west side.
Share August 9, 2024 on Facebook
Share August 9, 2024 on X (formerly Twitter)
Share August 9, 2024 on Linkedin
Email August 9, 2024 link
This project is substantially complete.