- Boring complete.
- July 22th working on SW corner.
- Veolia removing fire hydrant on southeast corner.
Share July 19, 2024 on Facebook
Share July 19, 2024 on Twitter
Share July 19, 2024 on Linkedin
Email July 19, 2024 link
This project is substantially complete.