April 17, 2026
- Intermountain Gas's work on Resseguie between 13th & 15th is expected to be done no later than May 1st.
- Once 13th-15th is done, 15th-16th will close for two weeks.
- The intersection of 15th & Resseguie will close for 2 days - date to be determined.
- Intermountain Gas has work from 9th to 12th - date to be determined.
- ACHD's contractor anticipates starting on the west end of the project June 1st.
Share April 17, 2026 on Facebook
Share April 17, 2026 on Twitter
Share April 17, 2026 on Linkedin
Email April 17, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends