April 17, 2026

  • Intermountain Gas's work on Resseguie between 13th & 15th is expected to be done no later than May 1st.
  • Once 13th-15th is done, 15th-16th will close for two weeks.
  • The intersection of 15th & Resseguie will close for 2 days - date to be determined.
  • Intermountain Gas has work from 9th to 12th - date to be determined.
  • ACHD's contractor anticipates starting on the west end of the project June 1st.