April 17, 2026
- Intermountain Gas's work on Resseguie between 13th & 15th is expected to be done no later than May 1st.
- Once 13th-15th is done, 15th-16th will close for two weeks.
- The intersection of 15th & Resseguie will close for 2 days - date to be determined.
- Intermountain Gas has work from 9th to 12th - date to be determined.
- ACHD's contractor anticipates starting on the west end of the project June 1st.
Share April 17, 2026 on Facebook
Share April 17, 2026 on X (formerly Twitter)
Share April 17, 2026 on Linkedin
Email April 17, 2026 link
This project is substantially complete.