Resseguie | Fort | 15th St: Pavement Preservation & ADA Project
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
-
March 13, 2026
Share March 13, 2026 on Facebook Share March 13, 2026 on Twitter Share March 13, 2026 on Linkedin Email March 13, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line, anticipated to begin the week of March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
March 9, 2026
Share March 9, 2026 on Facebook Share March 9, 2026 on Twitter Share March 9, 2026 on Linkedin Email March 9, 2026 linkIntermountain Gas is going to start lowering their gas line on Resseguie Street next week -13th Street to 15th Street: March 16th - April 3rd - 13th Street and 15th Street will remain open; 14th Street will be closed at Resseguie, with local access allowed at Ada St.15th Street to 16th Street: April 6th - April 17th. 15th Street and 16th Street will remain open for most of the work. 15th Street will need to be closed for 2 days. Exact dates and specific information to come soon.
-
February 12, 2026
Share February 12, 2026 on Facebook Share February 12, 2026 on Twitter Share February 12, 2026 on Linkedin Email February 12, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
February 5, 2026
Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 linkNo change to the project timeline.
-
January 30, 2026
Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
January 16, 2026
Share January 16, 2026 on Facebook Share January 16, 2026 on Twitter Share January 16, 2026 on Linkedin Email January 16, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
January 9, 2026
Share January 9, 2026 on Facebook Share January 9, 2026 on Twitter Share January 9, 2026 on Linkedin Email January 9, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
December 18, 2025
Share December 18, 2025 on Facebook Share December 18, 2025 on Twitter Share December 18, 2025 on Linkedin Email December 18, 2025 linkProject includes work on the following segments:
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
December 11, 2025
Share December 11, 2025 on Facebook Share December 11, 2025 on Twitter Share December 11, 2025 on Linkedin Email December 11, 2025 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring
-
December 4, 2025
Share December 4, 2025 on Facebook Share December 4, 2025 on Twitter Share December 4, 2025 on Linkedin Email December 4, 2025 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Photos
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org -
Supervisor, Construction
Phone 208-387-6100 Email connect@achdidaho.org




