Resseguie | Fort | 15th St: Pavement Preservation & ADA Project
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
-
July 9, 2026
Share July 9, 2026 on Facebook Share July 9, 2026 on X (formerly Twitter) Share July 9, 2026 on Linkedin Email July 9, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Work is expected to be done by the end of July. Resseguie is closed during the work. Sidewalk and roadway improvements resumed July 9th between 9th Street and 11th Street. Resseguie is closed during the work.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas’ work is complete between 9th and 11th Streets. Intermountain Gas will relocate their line between 11th and 12th Street beginning July 9th.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st and are anticipated to be done by the end of July. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street. Sidewalk and roadway improvements resumed June 1st and are anticipated to be done by the end of July. 15th Street is closed during the work.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Work is expected to be done by the end of July. Resseguie is closed during the work. Sidewalk and roadway improvements resumed July 9th between 9th Street and 11th Street. Resseguie is closed during the work.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas’ work is complete between 9th and 11th Streets. Intermountain Gas will relocate their line between 11th and 12th Street beginning July 9th.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st and are anticipated to be done by the end of July. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street. Sidewalk and roadway improvements resumed June 1st and are anticipated to be done by the end of July. 15th Street is closed during the work.
-
July 8, 2026 - Updated Detour Map and Information
Share July 8, 2026 - Updated Detour Map and Information on Facebook Share July 8, 2026 - Updated Detour Map and Information on X (formerly Twitter) Share July 8, 2026 - Updated Detour Map and Information on Linkedin Email July 8, 2026 - Updated Detour Map and Information linkStarting July 8th, Resseguie from 11th to 12th will be closed and is anticipated to re-open late July.
Intermountain Gas is installing utility improvements in advance of ACHD's project.
Please contact Intermountain Gas for questions.
Starting July 8th, Resseguie from 11th to 12th will be closed and is anticipated to re-open late July.
Intermountain Gas is installing utility improvements in advance of ACHD's project.
Please contact Intermountain Gas for questions.
-
July 1, 2026
Share July 1, 2026 on Facebook Share July 1, 2026 on X (formerly Twitter) Share July 1, 2026 on Linkedin Email July 1, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8 th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st o 15th Street is closed during the work.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8 th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st o 15th Street is closed during the work.
-
June 26, 2026
Share June 26, 2026 on Facebook Share June 26, 2026 on X (formerly Twitter) Share June 26, 2026 on Linkedin Email June 26, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st.15th Street is closed during the work.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st.15th Street is closed during the work.
-
June 18, 2026
Share June 18, 2026 on Facebook Share June 18, 2026 on X (formerly Twitter) Share June 18, 2026 on Linkedin Email June 18, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st. 15th Street is closed during the work.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st. 15th Street is closed during the work.
-
June 12, 2026
Share June 12, 2026 on Facebook Share June 12, 2026 on X (formerly Twitter) Share June 12, 2026 on Linkedin Email June 12, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st. 15th Street is closed during the work.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie is closed during their work. 10th Street is also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st. 15th Street is closed during the work.
-
June 5, 2026
Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is nearly complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie will be closed during their work. 10th Street will also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st.15th Street is closed during the work.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is nearly complete between 13th and 16th Streets. Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 8th. Resseguie will be closed during their work. 10th Street will also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements resumed June 1st.15th Street is closed during the work.
-
May 29, 2026 - Map and Information
Share May 29, 2026 - Map and Information on Facebook Share May 29, 2026 - Map and Information on X (formerly Twitter) Share May 29, 2026 - Map and Information on Linkedin Email May 29, 2026 - Map and Information link
Resseguie Street, 16th Street to 9th StreetPROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will complete relocating the gas line between 15th Street and 16th Street by June 2nd . Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 1st. Resseguie will be closed during their work. 10th Street will also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume June 1st . Fort Street will be closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume June 1st. 15th Street will be closed during the work.

Resseguie Street, 16th Street to 9th StreetPROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will complete relocating the gas line between 15th Street and 16th Street by June 2nd . Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 1st. Resseguie will be closed during their work. 10th Street will also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume June 1st . Fort Street will be closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume June 1st. 15th Street will be closed during the work.
-
May 21, 2026
Share May 21, 2026 on Facebook Share May 21, 2026 on X (formerly Twitter) Share May 21, 2026 on Linkedin Email May 21, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Intermountain Gas will complete work between 15th and 16th by next Friday, May 29th. ACHD's Contractor will start work on June 1 in the following areas:
Resseguie, 13th to 16th. 14th and 15th will be closed; 13th and 16th will remain open.
Fort, 15th to 16th
15th , Fort to Resseguie
Intermountain Gas will be starting work on June 1 on Resseguie, 9th to 11th. 10th Street will be closed; 9th Street and 11th Street will remain open.
UTILITY WORK: Veolia’s work is complete.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume on June 1st.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Intermountain Gas will complete work between 15th and 16th by next Friday, May 29th. ACHD's Contractor will start work on June 1 in the following areas:
Resseguie, 13th to 16th. 14th and 15th will be closed; 13th and 16th will remain open.
Fort, 15th to 16th
15th , Fort to Resseguie
Intermountain Gas will be starting work on June 1 on Resseguie, 9th to 11th. 10th Street will be closed; 9th Street and 11th Street will remain open.
UTILITY WORK: Veolia’s work is complete.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume on June 1st.
-
May 13, 2026
Share May 13, 2026 on Facebook Share May 13, 2026 on X (formerly Twitter) Share May 13, 2026 on Linkedin Email May 13, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK:
- Mainline pipe work is complete on Resseguie Street.
- Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK:
- Mainline pipe work is complete on Fort Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK:
- Mainline pipe work is complete on Resseguie Street.
- Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK:
- Mainline pipe work is complete on Fort Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Photos
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org -
Supervisor, Construction
Phone 208-387-6100 Email connect@achdidaho.org




