Resseguie | Fort | 15th St: Pavement Preservation & ADA Project
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
The Ada County Highway District (ACHD) will be reconstructing the following streets as part of the Pavement Preservation & ADA Project in Boise's North End. The work will start as early as mid-August 2025* and is expected to be complete in spring 2026.
- Resseguie St., 9th to 16th streets,
- Fort St., 16th St. to 15th St.
- 15th St., Fort St. to Resseguie St.
Project Description
- Rebuild Resseguie St and sections of Fort and 15th streets to replace the deteriorating pavement.
- Replace select sections of curb where trees will not be impacted.
- Install pedestrian ramps as needed to improve accessibility.
- Retain historic curb stamps wherever feasible.
*Schedule subject to change.
-
May 29, 2026 - Map and Information
Share May 29, 2026 - Map and Information on Facebook Share May 29, 2026 - Map and Information on Twitter Share May 29, 2026 - Map and Information on Linkedin Email May 29, 2026 - Map and Information link
Resseguie Street, 16th Street to 9th StreetPROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will complete relocating the gas line between 15th Street and 16th Street by June 2nd . Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 1st. Resseguie will be closed during their work. 10th Street will also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume June 1st . Fort Street will be closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume June 1st. 15th Street will be closed during the work.

Resseguie Street, 16th Street to 9th StreetPROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st between 13th Street and 16th Street. Resseguie will be closed between 13th Street and 16th Street during the work. 14th and 15th Streets will also be closed during the work. 13th and 16th Streets will remain open.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will complete relocating the gas line between 15th Street and 16th Street by June 2nd . Intermountain Gas will relocate the gas line between 9th Street and 11th Street beginning June 1st. Resseguie will be closed during their work. 10th Street will also be closed. 9th Street and 11th Street will remain open.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume June 1st . Fort Street will be closed during the work.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume June 1st. 15th Street will be closed during the work.
-
May 21, 2026
Share May 21, 2026 on Facebook Share May 21, 2026 on Twitter Share May 21, 2026 on Linkedin Email May 21, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Intermountain Gas will complete work between 15th and 16th by next Friday, May 29th. ACHD's Contractor will start work on June 1 in the following areas:
Resseguie, 13th to 16th. 14th and 15th will be closed; 13th and 16th will remain open.
Fort, 15th to 16th
15th , Fort to Resseguie
Intermountain Gas will be starting work on June 1 on Resseguie, 9th to 11th. 10th Street will be closed; 9th Street and 11th Street will remain open.
UTILITY WORK: Veolia’s work is complete.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume on June 1st.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Intermountain Gas will complete work between 15th and 16th by next Friday, May 29th. ACHD's Contractor will start work on June 1 in the following areas:
Resseguie, 13th to 16th. 14th and 15th will be closed; 13th and 16th will remain open.
Fort, 15th to 16th
15th , Fort to Resseguie
Intermountain Gas will be starting work on June 1 on Resseguie, 9th to 11th. 10th Street will be closed; 9th Street and 11th Street will remain open.
UTILITY WORK: Veolia’s work is complete.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume on June 1st.
-
May 13, 2026
Share May 13, 2026 on Facebook Share May 13, 2026 on Twitter Share May 13, 2026 on Linkedin Email May 13, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK:
- Mainline pipe work is complete on Resseguie Street.
- Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK:
- Mainline pipe work is complete on Fort Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK:
- Mainline pipe work is complete on Resseguie Street.
- Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK:
- Mainline pipe work is complete on Fort Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
May 8, 2026
Share May 8, 2026 on Facebook Share May 8, 2026 on Twitter Share May 8, 2026 on Linkedin Email May 8, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
May 1, 2026
Share May 1, 2026 on Facebook Share May 1, 2026 on Twitter Share May 1, 2026 on Linkedin Email May 1, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work. Work was completed May 1. Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work. Work was completed May 1. Intermountain Gas will continue relocating the gas line between 15th Street and 16th Street, beginning May 4th.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
April 24, 2026
Share April 24, 2026 on Facebook Share April 24, 2026 on Twitter Share April 24, 2026 on Linkedin Email April 24, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume on June 1st
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
April 17, 2026
Share April 17, 2026 on Facebook Share April 17, 2026 on Twitter Share April 17, 2026 on Linkedin Email April 17, 2026 link- Intermountain Gas's work on Resseguie between 13th & 15th is expected to be done no later than May 1st.
- Once 13th-15th is done, 15th-16th will close for two weeks.
- The intersection of 15th & Resseguie will close for 2 days - date to be determined.
- Intermountain Gas has work from 9th to 12th - date to be determined.
- ACHD's contractor anticipates starting on the west end of the project June 1st.
- Intermountain Gas's work on Resseguie between 13th & 15th is expected to be done no later than May 1st.
- Once 13th-15th is done, 15th-16th will close for two weeks.
- The intersection of 15th & Resseguie will close for 2 days - date to be determined.
- Intermountain Gas has work from 9th to 12th - date to be determined.
- ACHD's contractor anticipates starting on the west end of the project June 1st.
-
April 10, 2026
Share April 10, 2026 on Facebook Share April 10, 2026 on Twitter Share April 10, 2026 on Linkedin Email April 10, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK:
- Mainline pipe work is complete on Resseguie Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK:
- Mainline pipe work is complete on Fort Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK:
- Mainline pipe work is complete on Resseguie Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK:
- Mainline pipe work is complete on Fort Street.
- Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK:
- Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
April 2, 2026
Share April 2, 2026 on Facebook Share April 2, 2026 on Twitter Share April 2, 2026 on Linkedin Email April 2, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
-
March 26, 2026
Share March 26, 2026 on Facebook Share March 26, 2026 on Twitter Share March 26, 2026 on Linkedin Email March 26, 2026 linkResseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Detour Map - May 2026
Photos
Who's Listening
-
Sr. Project Manager
Phone 208-387-6100 Email connect@achdidaho.org -
Supervisor, Construction
Phone 208-387-6100 Email connect@achdidaho.org




