April 2, 2026
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas is relocating the gas line beginning March 16th between 13th Street and 15th Street. Resseguie will be closed during the work.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.
UTILITY WORK: Veolia’s work is complete.
15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring.
Share April 2, 2026 on Facebook
Share April 2, 2026 on Twitter
Share April 2, 2026 on Linkedin
Email April 2, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends