August 1, 2025

  • Project includes work on the following segments:
  • Resseguie Street, 16th Street to 9th Street. Veolia will be closing the intersection of Resseguie & 13th Street on Aug 8th – 11th to get the intersection done before school starts.
  • Veolia will be closing Resseguie between 13th and 15th on August 12th -23rd. 13th Street and 15th Street will be open during this phase. 14th Street will be closed.
  • Veolia will be closing Resseguie between 15th and 16th on August 25 th – Sept 5 th. 15th Street will be closed during this phase.
  • Fort Street, 16th Street to 15th Street
  • 15th Street, Fort Street to Resseguie Street