Project includes work on the following segments: oResseguie Street, 16th Street to 9th Street

PROJECT WORK: The intersection of Resseguie Street & 9th Street will be closed August 18th – 26th for pipe replacement work. Resseguie Street will be closed from 11th and 13th on August 25th – September 30th for roadway improvements. UTILITY WORK: Veolia will be closing Resseguie between 13th and 15th on August 12th -23rd. 13th Street and 15th Street will be open during this phase. 14th Street will be closed. Veolia will be closing Resseguie between 15th and 16th on August 25th – Sept 5th. 15th Street will be closed during this phase. Fort Street, 16th Street to 15th Street. 15th Street, Fort Street to Resseguie Street.