August 7, 2026
- Resseguie Street, 16th Street to 9th Street
- PROJECT WORK:
- Resseguie, 13th Street and 16th Street is substantially complete.
- The intersection of Resseguie & 13th Street is closed August 5th – August 10th.
- Sidewalk and roadway improvements between 9th Street and 12th Street are on-going.
- Resseguie is closed during the work.
- UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas’ work is complete between 13th and 16th Streets.
- Intermountain Gas’ work is complete between 9th and 10th Streets.
- ntermountain Gas work is on-going between 10th and 12th Streets.
- PROJECT WORK:
- Fort Street, 16th Street to 15th Street
- Substantially completed on July 31st.
- 15th Street, Fort Street to Resseguie Street
- Substantially completed on July 31st.
Share August 7, 2026 on Facebook
Share August 7, 2026 on X (formerly Twitter)
Share August 7, 2026 on Linkedin
Email August 7, 2026 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends