- Resseguie Street, 16th Street to 9th Street
- PROJECT WORK:
- Resseguie, 13th Street and 16th Street is substantially complete.
- The intersection of Resseguie & 13th Street is closed August 5th – August 10th.
- Sidewalk and roadway improvements between 9th Street and 12th Street are on-going.
- Resseguie is closed during the work.
- UTILITY WORK:
- Veolia’s work is complete.
- Intermountain Gas’ work is complete between 13th and 16th Streets.
- Intermountain Gas’ work is complete between 9th and 10th Streets.
- ntermountain Gas work is on-going between 10th and 12th Streets.
- PROJECT WORK:
- Fort Street, 16th Street to 15th Street
- Substantially completed on July 31st.
- 15th Street, Fort Street to Resseguie Street
- Substantially completed on July 31st.