August 8, 2025

Project includes work on the following segments:

  • Resseguie Street, 16th Street to 9th Street - Veolia will be closing the intersection of Resseguie & 13th Street on Aug 8th – 11th to get the intersection done before school starts.
  • Veolia will be closing Resseguie between 13th and 15th on August 12th -23rd.
  • 13th Street and 15th Street will be open during this phase. 14th Street will be closed.
  • Veolia will be closing Resseguie between 15th and 16th on August 25th – Sept 5th. 15th Street will be closed during this phase.
  • Fort Street, 16th Street to 15th Street o 15th Street, Fort Street to Resseguie Street
Share August 8, 2025 on Facebook Share August 8, 2025 on Twitter Share August 8, 2025 on Linkedin Email August 8, 2025 link