December 11, 2025

Resseguie Street, 16th Street to 9th Street

PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements will resume in the spring.

UTILITY WORK: Veolia’s work is complete. Intermountain Gas will lower the gas line in the spring of 2026.

Fort Street, 16th Street to 15th Street

PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements will resume in the spring.

UTILITY WORK: Veolia’s work is complete.

15th Street, Fort Street to Resseguie Street - Sidewalk and roadway improvements will resume in the spring