July 30, 2026
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Resseguie, 13th Street and 16th Street is substantially complete. The intersection of Resseguie & 13th Street will be closed August 3rd – August 10th. Sidewalk and roadway improvements between 9th Street and 12th Street are on-going. Resseguie is closed during the work.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas’ work is complete between 9th and 10 th Streets. Intermountain Gas work is on-going between 10th and 12th Streets.
Fort Street, 16th Street to 15th Street - Substantially completed on July 31st.
15th Street, Fort Street to Resseguie Street - Substantially completed on July 31st.