July 9, 2026
Resseguie Street, 16th Street to 9th Street
PROJECT WORK: Mainline pipe work is complete on Resseguie Street. Sidewalk and roadway improvements resumed June 1st between 13th Street and 16th Street. Work is expected to be done by the end of July. Resseguie is closed during the work. Sidewalk and roadway improvements resumed July 9th between 9th Street and 11th Street. Resseguie is closed during the work.
UTILITY WORK: Veolia’s work is complete. Intermountain Gas’ work is complete between 13th and 16th Streets. Intermountain Gas’ work is complete between 9th and 11th Streets. Intermountain Gas will relocate their line between 11th and 12th Street beginning July 9th.
Fort Street, 16th Street to 15th Street
PROJECT WORK: Mainline pipe work is complete on Fort Street. Sidewalk and roadway improvements resumed June 1st and are anticipated to be done by the end of July. Fort Street is closed during the work.
UTILITY WORK: Veolia’s work is complete. 15th Street, Fort Street to Resseguie Street. Sidewalk and roadway improvements resumed June 1st and are anticipated to be done by the end of July. 15th Street is closed during the work.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends